IBAKH (Int' Engineering and Procurement Bureau)

Engineering Supervision of the Erection and Commissioning Works for Ingula Pumped Storage Scheme as South Africa’s largest hydro power project to date, 2016

Engineering Supervision of the Erection and Commissioning Works for Ingula Pumped Storage Scheme as South Africa’s largest hydro power project to date, 2016

May 7, 2016
Operation of a pumped storage scheme
 
IBAKH is participating in Engineering Supervision of the Erection and Commissioning Works for Ingula Pumped Storage Scheme. The project site is located in north-east of Van Reenen's Pass, spanning the escarpment of the Little Drakensberg, and straddling the provincial boundary of the Free State and KwaZulu-Natal (KZN) provinces near the town of Ladysmith in South Africa. Site selection studies began in the 1980s and construction began in 2005. This project site location is also the continental watershed between the Vaal River catchment, flowing into the Atlantic Ocean, and the Thukela River catchment, flowing into the Indian Ocean. This scheme is the first of its kind in South Africa and designed to provide power to the high-voltage electric power transmission network (National Grid) during peak demand periods.

The main civil contractor as CMI JV, comprising CMC di Ravenna, PG Mavundla and Impregilo (underground civil works) led by Italian firms, has been awarded a contract by Eskom to construct the underground works and reservoirs for the Ingula project in March 2009 and project was originally scheduled to come on line during 2012, with a unit being commissioned each quarter, but in Jul 2009, the schedule was slipped a year for completion in 2013. This schemed is constructed by an Eskom (Owner and Operator) and CMI JV at a cost of USD3.5 billion. CMC Mavundla constructed main access tunnel.

This scheme comprises the Bedford Dam/Upper Reservoir, located in a tributary of the Wilge River, and the Bramhoek Dam/Lower Reservoir, situated in a tributary of the Klip River. Construction of the Bramhoek Dam used the Grout Enriched Roller Compacted Concrete (GE-RCC) and completed in November 2011, while the Bedford Dam used a concrete-faced rockfill design and completed in April 2011. Each reservoir, is capable of holding approximately 22 million cubic metres of water. Two reservoirs, 4.6km apart, are connected by underground waterways. The elevation between the two reservoirs affords a hydraulic head of 460 m with 80 m submergence. A 2 km long twin headrace tunnels(concrete and steel-lined: 6,6 m - nominal dia penstocks) connects the upper reservoir to the underground power station(The largest mudrock cavern in the world, totalling 200,000m³ : 150 m x 25 m main cavern together with a 160 m x 15 m transformer hall) which house 4 pump-turbine units. Water from the power station is discharged down Steel-lined extended draft tubes and a single 2.5 km long concrete-lined tailrace tunnel (9,0 m nominal dia.) to the lower reservoir. To generate electricity during times of peak demand, water is released from the upper reservoir, passing through the pump/turbines, into the lower reservoir. During times of low energy demand, the pump-turbines are used to pump the water from the lower reservoir, back to the upper reservoir.

This new 1334 MW pumped storage scheme is designed by a three-way Braamhoek Consultants Joint Venture (BCJV) as main project supervisor, consisting of Arcus GIBB (Pty), Stewart Scot International (SSI Engineers and Environmental Consultants, now known as Royal Haskoning) and Knight Piésold(design phases 1 and 2, construction design, supervision and dam construction):

GIBB responsibilities as leader of BCJV are: civil, mechanical and electrical engineering, detailed design, tender documentation, on-site design monitoring of access roads, dams, tunnels, caverns, mechanical and electrical works and construction supervision of all aspects of the project.

Royal HaskoningDHV has been involved at Ingula since the project began in 2005, as part of Braamhoek Consultants, a joint venture company set up to deliver five contracts within the bigger project. These include design and construction supervision for Ingula’s two dams – Bramhoek and Bedford, access roads, visitors centre and administration building and main underground works.

Knight Piésold was responsible for project management, dam type selection, geotechnical investigations, dam design, tender documents, construction supervision, and Operations and Maintenance Manuals.

Eskom has awarded a contract to Consortium of Voith Siemens Hydro and Fuji Hydro Power Generation in September 2008 for the main generating plant equipment supply to the Ingula project(pump-turbines, motor-generators and mechanical auxiliary plant). The contract is valued at €140-million (R1.65-billion). It had concluded a loan worth approximately R1 billion with the DB (Deutsche Bank) to fund 85 percent of the pump-turbines contract. DCD Heavy Engineering manufactured four Spiral Casings for Voith Siemens Hydro Power Generation and equiped Ingula pumped-storage project. Consortium of Voith Siemens Hydro and Fuji Hydro supplied the complete electro-mechanical equipment. This included four reversible Francis pump-turbines from Heidenheim of Germany, each with a capacity of 342 MW, the associated motor-generators (Manufactured at the Japanese plant in Kawasaki), as well as the entire control and automation systems. Recently Nippa Tech has signed a contract with Fuji Voith for Site Coordination and consulting for Ingula project site activities on motor-generator.

Here are other involved Sub-contractors and suppliers:
ABB (electrical balance of plant); Murray & Roberts (exploratory tunnel); Grinaker-LTA (access roads); Afriscan (water supply, sewage treatment, small access roads and building temporary Eskom offices); B&E Quanza Group (aggregate quarry); Acer [Africa] (environmental consultants); Braamhoek Dam JV (BDJV), comprising Concor Roads & Earthworks, Wilson Bayley Holmes-Ovcon, Edwin Construction and Silver Rock (dam contract); NCC Environmental Services (independent environmental control officer services); Konecranes (heavy-duty cranes); Letacla (fibre-optic communications); Siemens (generator transformers); Roshcon (line integration – main contractor); Optipower and Babcock Ntuthuko (line integration – subcontractors); and CBI and Prysmian (supply and installation of of 400 kV cables); RW Business Enterprises (surface drilling for dams); Drillcon (deep drilling for waterways); ABN Amro (business case review); Concor Mining and Murray & Roberts (exploration tunnel); T Patridge (geotechnical review); BKS (dam review); V Pysikowski (hydromechanical review); C Zdziarski (HVAC review); Grinaker/LTA (access roads); Afriscan (advanced infrastructure); B&E Quanza Group joint venture (quarry) and ARQ Consulting Engineers.

The schedule was slipped more thereafter to begin operations in late 2015, but the pump-turbine/motor-generator units were not commissioned as planned. The new target is set to have all four units commercially operational by July 2017. Unit-3 was synchronized on 6 Mar 2016.
 

IBAKH (Engineering Bureau) is planning to provide services as a sole proprietorship firm, 2015

June 3, 2015
 

Construction of ILISU Dam and Hydro-Power Plant on the Tigris river in the Southeastern Turkey, 2012-2013

May 7, 2013


 The physical model of ILISU Dam and Hydro-Power Plant Project

IBAKH GmbH has participated in Engineering Supervision of the Fabrication and Erection of Hydro-Mechanical Equipment in ILISU Dam and Hydro-Power Plant Project in the Southeastern Turkey since end of April 2012. This project is under construction(84 months turnkey design and construction contract) by consortium led by Turkish civil construction company. The main Dam is CFRD (Concrete Face Rockfill Dam) of 135 m height and 1,820 m length and cofferdam has 30 m height to protect the main construction zone. The total storage capacity is 7.4 billion m3, to feed powerhouse which has six vertical Francis Turbine-Generator sets consisting governors, 5100 mm Diameter Butterfly valves and excitation systems to produce 3,833 GWh of annual peak electrical energy. 

The Hydraulic Energy-Carrying Penstock has Diameter of 10 m and total weight of 6,630 ton. The powerhouse has two cranes of 250 / 15 ton lifting capacity. Each vertical Francis Turbine has Runner Diameter of 4300 mm and its output is  204 / 222 MW (rated / maximum) at Design Head of 110 m and rated speed of 187.5 rpm. Total weight of each Generator is 795 tons and its heaviest component is rotor of 449 tons. Its Stationary Winding Diameter is 10500 mm. Each Generator has rated output of 223 MVA and output voltage of 13.8 kV at the same rated speed of vertical Francis Turbine. There is one horizontal Francis Turbine(runner diameter of 848 mm) as Auxiliary unit which has output of  4.5 MW / 5.5 MVA at the same Design Head of main units (110 m) and higher rated speed of 750 rpm.

19 Single phase step up transformers(Output of 223 / 3 MVA and Voltage Ratio of 13.8 / 380 kV) will supply the electricity at 380 kV.  Also two Coupling auto-transformers(Output of 250 MVA and Voltage Ratio of 154 / 380 kV) will supply the electricity at 154 kV. Output Electric Power of Transformers will be transmitted to the switchyard(Double busbars with transfer bus) through a short power transmission line of 900 m length and later will be fed to national electric power transmission grid from this switchyard through  21 bays at two voltage levels of 380 kV(13 bays plus three spare) and 154 kV(8 bays plus two spare). The estimated weight of steel structures for towers and portals is ca. 700 tons.
 
After detailed inspection of Diversion Tunnel Outlet Gates(From Dicle Dam) and hard working on Fabrication and Erection of relevant embedded parts in diversion tunnels and missing the dry tests(in both inlet and outlet), the Tigris river is diverted on 28.9.2012 through three diversion tunnels, each with 12 m diameter and approximately 1,000 m length to ensure a dry construction zone. Two tunnels will be closed by concrete plug. The third one will be operated as Low Level Bottom Outlet. Immediately after river diversion, the construction of powerhouse drainage gallery and installation of its relevant piping started which followed by transferring the fabricated penstock segments from site fabrication shop and erection in power tunnels and powerhouse. Site Fabrication Processes are controlled and relevant Engineering Supervisions are performed properly.

 

IBAKH as Limited Liability Company (GmbH)

May 4, 2012

IBAKH as sole proprietorship firm is dissolved in April 2012 and at the same time, IBAKH registered as Limited Liability Company (Gesellschaft mit beschränkter Haftung: GmbH). IBAKH GmbH is allowed to establish subsidiaries and affiliated companies, to hold interests and stakes in other companies, to acquire, burden, divest and administer property, to execute financing for its own account or for the account of a third party, as well as to issue guarantees and securities for affiliated companies and third party entities.

 

Rehabilitation of Hinterrhein Hydro-Power Plants in the Swiss Alps, 2011-2012

January 8, 2012


Heart of the plant: The Valle di Lei reservoir

IBAKH is participating in Engineering Supervision of Overall Rehabilitation of Hinterrhein Hydro-Power Plants (Gesamterneuerung der Wasserkraftanlagen) in Thusis Region of Canton Graubünden in the Swiss Alps since October 1, 2011. The Kraftwerke HinterRhein AG (KHR), built between 1956 and 1963 at a cost of some CHF 620 million, is a three-level Hydro-Power Plant group. With the Hydro-Power Plants at Ferrera, Bärenburg and Sils, KHR operates the biggest power plant combination in the canton of Graubünden with a total installed capacity of approximately 650 MW – and with the 220/380 kV outdoor switchgear plant in Sils as a key junction in the Swiss and European electricity network.  These power plants have been in operation for more than 40 years.  KHR uses the potential energy of water from 1,931 meters above sea level in the Valle di Lei valley to 667 meters above sea level in Sils. The heart of the plant is the Valle di Lei reservoir, which holds about 200 million m³. The Thusis power plant, constructed between 1966 and 1968, is also included in the plant group. It uses the spike and residue water remaining in the Posterior Rhine.


 

Joint cooperation of IBAKH and SeWa in Energy Sector, West Africa, 2011

January 7, 2012

Director IBAKH, Business Development Manager and Technical Manager SeWa, in Power Plant of Industrial Factory, Nigeria, West Africa, November 15, 2011.

Following the strategy to penetrate the West Africa market in the Energy sector, IBAKH (International Engineering-Bureau, Switzerland) and SeWa (Steag Encotec West Africa, Nigeria) have signed a cooperation agreement aimed at furthering joint cooperation in Power Plant Industry and Technology(2011).   The memorandum, which was signed by IBAKH Director  Yousef Asadi-Khiavi and SeWa Chairman John Appleby, is the first formal cooperation agreement between these two entities.    Later IBAKH Director had a Technical visit in one of Gas Turbine Power Plants in West Africa accompanied by Business Development Director and Project Manager of SeWa.     IBAKH and SeWa will work together for future power plant projects in West Africa by providing integrated services for the, repair and overhaul of industrial and aero turbines and related components and accessories (IBAKH) and carrying on the business of the provision of engineering consultancy as well as operations and maintenance services to the energy and power generation markets (SeWa).

 

Al-Anbar 2nd Annual International Investment Conference 2011, Turkey

October 30, 2011
Al-Anbar 2nd Annual International Investment Conference 2011, Turkey

Director of IBAKH and Iraqi Managing Directors, Istanbul, October 24, 2011.

Investment in Al Anbar(the largest Iraqi Province) this year(2011) had reached $2 billion in the sectors of housing, agriculture and industry, a number that is expected to double in the coming months as a result of the planning by Al-Anbar Investment Commission to establish multiple industrial cities in Ramadi, Anna and Hīt.  Al-Anbar Investment Commission announced 2nd Annual International Investment Conference(October 2011 - Istanbul/Turkey) and IBAKH participated in this Conference. The Conference opened new horizons for an all-out investment in Al-Anbar, the largest Iraqi Province, in various sectors, especially in the fields of oil and natural gas. Major local, Arab and international investment companies were taking part in this conference to take advantage of these rare investment opportunities now available in Al Anbar, and the unprecedented incentives offered by the Iraqi government to investors.
IBAKH learned about the various industrial projects expected to be launched in the industrial cities of Al-Anbar, which announced during the conference. Al-Anbar is a promising investment attraction because of its outstanding geographical location near Baghdad and its border with three countries, which appeals to investors to create new and competitive markets. The Province has adopted long-term investment strategies aiming at employing the unique resources and assets of Al-Anbar, a city renowned for its well-established and diverse industrial activities.
 

LASER World of PHOTONICS 2011, Germany

July 2, 2011
LASER World of PHOTONICS 2011, Germany

Among those on hand for the World of Photonics opening were, from left above, Yousef Asadi-Khiavi (Director IBAKH), World of Photonics Steering Committee Chair Peter Loosen (Fraunhofer-Institut für Lasertechnik), SPIE President-Elect Eustace Dereniak (Univ. of Arizona College of Optical Sciences), and Peter Moulton (Q-Peak).


 

20th International Congress on Photonics in Europe—collocated with LASER World of PHOTONICS 2011

The World of Photonics Congress (May 22-26, 2011) featured some of the most well-known events in the sector for optical technologies.  The congress consists of the following conferences and events:

-CLEO®/Europe – EQEC (organized by EPS, OSA, IEEE Photonics Society)

-European Conferences on Biomedical Optics (ECBO)  (organized by SPIE and OSA and the Deutsche Gesellschaft für Lasermedizin  [DGLM] as a cooperating organization)

-Optical Metrology (organized by SPIE Europe)

-Lasers in Manufacturing (LiM 2011) (organized by WLT)

-1st European Optical Society (EOS) Conference on Optofluidics (EOSOF)

-2nd European Optical Society (EOS) Conference on Manufacturing of Optical Components (EOSMOC)

-Application Panels—Lasers and Photonics in Actual Practice (organized by MMG & its partners) http://spie.org/x48565.xml

 

To penetrate the Middle-East market, Energy sector, 2011

June 27, 2011
To penetrate the Middle-East market, Energy sector, 2011
Director IBAKH and CEO INOVA, in front of the Ministry of Electricity, Baghdad, May 03, 2011, 350 MW Diesel Power Plant Project (Finance and Investment Advisory Meeting).
 
Following new strategy to penetrate the Middle-East market, specifically in the Energy sector, IBAKH and its partner INOVA (UAE) have successfully paved the way for new business through fruitful discussions and negotiations of agreements in principle with the Ministry of Electricity and the National Investment Commission in Baghdad. IBAKH and INOVA will team up for future projects in Iraq by providing EPC services (IBAKH) and funding (INOVA) for temporary, brownfield, rehabilitation and green field energy projects. Both IBAKH and INOVA will take advantage of their vast networks in the Middle-East and Europe.
 
 

About Me